G99 grid connection in Yorkshire: Northern Powergrid explained

Before most commercial solar systems in Yorkshire can be switched on, the network operator has to approve the connection. That approval is called G99. This page explains how that works on Northern Powergrid’s Yorkshire network, for farms, schools, warehouses and other rooftop systems of about 30 to 500 kWp. The longer national process guide remains on brightedgesolar.com.

Call 01482 765063 or email max@brightedgesolar.com if you want the likely connection position for a particular site.

Industrial rooftop solar array in Doncaster.

The process, in short

  1. When G98 is enough. Only very small systems, at or below 16 amps per phase (about 3.68 kW on a single-phase supply, or 11.04 kW on three-phase), can usually follow the G98 connect-and-notify route.
  2. When G99 is required. Almost every commercial system on this site is larger than that threshold, so a G99 application has to be approved before installation.
  3. What BrightEdge submits. BrightEdge prepares and submits the application to Northern Powergrid, with the system design and the site details the operator needs.
  4. What happens if export is limited. The usual options are export limitation, or sizing the array more closely to what the site uses. A limit does not automatically kill the case, but it should be modelled before anyone orders kit.

In BrightEdge’s experience the application typically adds eight to twelve weeks before installation. That is their typical timescale, not an official Northern Powergrid service standard. Position last checked 10 November 2026.

Who the network operator is

Northern Powergrid runs the electricity distribution network across Yorkshire and northern Lincolnshire, including the East Riding, Hull, York and North Yorkshire, West Yorkshire and South Yorkshire. If your site is in that area, the G99 application goes to them, not to your energy supplier.

G98 or G99?

The Energy Networks Association sets the rules. G98 covers small, fully type-tested generators at or below 16 amps per phase, which is 3.68 kW per phase — about 3.68 kW on a single-phase supply, or 11.04 kW on three-phase. Anything larger needs a G99 application approved before the system is installed. Almost every commercial array in the size range this site covers will need G99.

What the application involves

BrightEdge checks the supply, existing meters and any earlier approvals, then designs the system and prepares the application, including the technical details, equipment data and single-line diagrams Northern Powergrid needs. The operator studies the effect on the local network and comes back with a connection offer. That offer may approve the full export, approve it with an export limit, or require network work at a cost.

In BrightEdge’s experience, G99 approval typically adds eight to twelve weeks before installation, and can take longer where the network is constrained or the operator asks questions. That timescale is their typical experience, not a published Northern Powergrid service standard. They start the application early for that reason. Any fees charged by the operator are shown separately in the quote.

Once the offer is accepted and the system is installed, it is tested and commissioned to G99 requirements and the paperwork is sent back to Northern Powergrid. On larger systems the operator may want to witness the tests. BrightEdge handles that commissioning paperwork as part of the project, alongside the original application.

If export is limited

A limited offer does not have to stop a project. Export limitation (G100) uses a controller to hold the export at the agreed level, while you still use everything you generate on site. The array can also be sized more closely to on-site use. On rural parts of the Wolds and similar areas, longer, lower-capacity lines make this conversation more common. The 29 kWp ground-mounted array at Wapplington, near Pocklington, uses a Solis Export Power Manager for exactly this. On an 86 kWp industrial roof in Doncaster, BrightEdge sized the new inverter to fit an existing G99 approval granted for an older 60 kW unit, and added export limitation.

This page does not set out to sell battery storage. Storage can be a later conversation where the usage pattern supports it, but it is not a requirement of a workable G99 offer.

Frequently asked questions

If it can export more than 16 amps per phase, yes. Almost every commercial system does.

BrightEdge says it typically adds eight to twelve weeks before installation, sometimes longer on constrained networks. That is their experience with Northern Powergrid, not an official guaranteed timescale.

BrightEdge does, as part of the project, and deals with any questions from the operator.

They may limit your export or ask for network upgrades. Export limitation, or a smaller array, can often keep the project within the offer.

Northern Powergrid, across Yorkshire and northern Lincolnshire. See also the areas page.

Enquiries

Get a commercial solar assessment

Send your site address and a recent electricity bill, or half-hourly data if you have it. BrightEdge will come back with an initial layout and estimate, then arrange a survey if it is worth pursuing.

Call 01482 765063 or email max@brightedgesolar.com.

BrightEdge Solar Ltd, Beverley. MCS certified (NIC-601602). CHAS Elite. RECC. NICEIC. 24-month commercial workmanship warranty.

Ask about your roof

A four-step enquiry form. Notifications go to max@brightedgesolar.com. Phone is optional.

Tell us one of these, or both.
I can send a bill or half-hourly data
An outward code is enough, for example HU17, LS12 or S9.