A BrightEdge Solar guide
Call 01482 765063 or email max@brightedgesolar.com if you want the likely connection position for a particular site.
In BrightEdge’s experience the application typically adds eight to twelve weeks before installation. That is their typical timescale, not an official Northern Powergrid service standard. Position last checked 10 November 2026.
Northern Powergrid runs the electricity distribution network across Yorkshire and northern Lincolnshire, including the East Riding, Hull, York and North Yorkshire, West Yorkshire and South Yorkshire. If your site is in that area, the G99 application goes to them, not to your energy supplier.
The Energy Networks Association sets the rules. G98 covers small, fully type-tested generators at or below 16 amps per phase, which is 3.68 kW per phase — about 3.68 kW on a single-phase supply, or 11.04 kW on three-phase. Anything larger needs a G99 application approved before the system is installed. Almost every commercial array in the size range this site covers will need G99.
BrightEdge checks the supply, existing meters and any earlier approvals, then designs the system and prepares the application, including the technical details, equipment data and single-line diagrams Northern Powergrid needs. The operator studies the effect on the local network and comes back with a connection offer. That offer may approve the full export, approve it with an export limit, or require network work at a cost.
In BrightEdge’s experience, G99 approval typically adds eight to twelve weeks before installation, and can take longer where the network is constrained or the operator asks questions. That timescale is their typical experience, not a published Northern Powergrid service standard. They start the application early for that reason. Any fees charged by the operator are shown separately in the quote.
Once the offer is accepted and the system is installed, it is tested and commissioned to G99 requirements and the paperwork is sent back to Northern Powergrid. On larger systems the operator may want to witness the tests. BrightEdge handles that commissioning paperwork as part of the project, alongside the original application.
This page does not set out to sell battery storage. Storage can be a later conversation where the usage pattern supports it, but it is not a requirement of a workable G99 offer.
If it can export more than 16 amps per phase, yes. Almost every commercial system does.
BrightEdge says it typically adds eight to twelve weeks before installation, sometimes longer on constrained networks. That is their experience with Northern Powergrid, not an official guaranteed timescale.
BrightEdge does, as part of the project, and deals with any questions from the operator.
They may limit your export or ask for network upgrades. Export limitation, or a smaller array, can often keep the project within the offer.
Northern Powergrid, across Yorkshire and northern Lincolnshire. See also the areas page.
Enquiries
Send your site address and a recent electricity bill, or half-hourly data if you have it. BrightEdge will come back with an initial layout and estimate, then arrange a survey if it is worth pursuing.
Call 01482 765063 or email max@brightedgesolar.com.
BrightEdge Solar Ltd, Beverley. MCS certified (NIC-601602). CHAS Elite. RECC. NICEIC. 24-month commercial workmanship warranty.
A four-step enquiry form. Notifications go to max@brightedgesolar.com. Phone is optional.